Business & Products
 
Home | Business&
Products
| Modules & Skids

SH services to the benefit for our customers are extended to Piping Modules for the same satisfaction as proven for piping packages.

The newest service in our portfolio brings you the advantage of piping Modules including the basic piping and support package with our strengths based on the well trained and experienced engineers of project management in power plants.

The module design considers installation requirements, even in confined areas, considerably reducing erection time on site compared with the usual trade-wise erection sequence while modular piping solution offers several benefits, including flexibility in plant siting, less safety concern during construction, and ease of equipment modification lowering costs by shifting high cost field labor hours to a fabrication yard and benefit from higher productivity.
Efficiencies in cost and material
Robust designs with scalability
Reduces field labour and risk associated with time
Faster to install and commission
Lower welding cost
Coatings, heat tracing insulation and instrumentation are performed in the shop environment
Safer to erect
Main Pipe Rack
Cooling Water
Condensate Recirculation Pump
Water System
Steam Turbine Drain
Feed Water Pump
Auxiliary System
Clean Drain Skid
UTE GNA I THERMOELECTRIC POWER PROJECT (1,238MW X 1 UNIT)
End User : UTE GNA I Gás Natural AÇu S.A.
Customer : SIEMENS
Location : North of Rio de Janeiro State, Brazil
Working Period : 2018. 03.~2019. 04.
Volume Performed : 2,293 tons
77 Transportation Units with 12 modules.